| Assessment Year | 1992 |
|---|---|
| Principal Product | SCREENING/SIFTING EQUIPMENT |
| NAICS |
n/a
|
| SIC | 3569: General Industrial Machinery and Equipment, Not Elsewhere |
| Sales Range | $10 M to 50M |
| # of Employees | 117 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,250
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $132,445 | 2,097,597 |
kWh
|
$0.063 |
| Fuel Oil #2 | $11,475 | 1,890 |
MMBtu
|
$6.07 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $5,982 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $1,452 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $500 | $1,500 |
$500
-
kWh
|
- | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $810 | - |
$810
-
kWh
|
- | |
| 03 | 2.6232: Install set-back timers | $952 | - |
$1,110
14,361
kWh
|
$(-158.0)
-
MMBtu
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,720 | $8,620 |
$4,290
55,686
kWh
|
$(-570.0)
-
MMBtu
|
|
| TOTAL RECOMMENDED | $5,982 | $10,120 |
$6,710
70,047
kWh
|
$(-728.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $1,452 | $1,500 |
$1,610
14,361
kWh
|
$(-158.0)
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs