ITAC Assessment: UD0343
ITAC logo
ITAC Assessment: UD0343
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1991
Principal Product FUSES FOR MISSILES
NAICS
n/a
SIC 3679: Electronic Components, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 300
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 4,200
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $83,904 1,459,261
kWh
Natural Gas $5,575 1,210
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,132 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4239: Eliminate or reduce compressed air usage $801 $100 $801
26,671
kWh
- -
02 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $1,695 - - - $1,695
03 2.6232: Install set-back timers $1,735 - $1,530
50,996
kWh
- $205
04 2.7494: Install storm windows and doors $1,587 $1,100 - $1,587
-
MMBtu
-
05 3.4151: Minimize water usage $2,314 - - - $2,314
TOTAL RECOMMENDED $8,132 $1,200 $2,331
77,667
kWh
$1,587
-
MMBtu
$4,214
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs