| Assessment Year | 2022 |
|---|---|
| Principal Product | Seafood Proceesing |
| NAICS | 311710: Seafood Product Preparation and Packaging |
| SIC | 2092: Prepared Fresh or Frozen Fish and Seafoods |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
39,704
ft2
|
| Annual Production | 247
ton
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $275,169 | 4,655,200 |
kWh
|
$0.059 | |
| Electricity Demand | $128,855 | 8,992 |
kW-mo/yr
|
$14.33 | |
| Electricity Fees | $67,094 | - |
|
- | |
| Waste Disposal Costs | |||||
| Water Usage | $224,009 | 15,903 |
Tgal
|
$14.09 | |
| TOTAL YEARLY COSTS | $695,127 | ||||
| RECOMMENDED SAVINGS* | $50,771 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $4,554 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.9112: Use solar heat to heat water | $24,802 | $108,191 |
$24,802
420,369
kWh
|
- | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $19,919 | $1,980 |
$14,932
253,092
kWh
|
$4,987
-
kW-mo/yr
|
- | |
| 03 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $3,003 | $14,690 |
$(-767.0)
(-13,000)
kWh
|
- | $3,770 | |
| 04 | 2.7232: Replace existing hvac unit with high efficiency model | $1,496 | $240 |
$1,009
17,107
kWh
|
$487
-
kW-mo/yr
|
- | |
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,094 | $1,885 |
$822
13,933
kWh
|
$272
-
kW-mo/yr
|
- | |
| 06 | 2.7135: Install occupancy sensors | $235 | $700 |
$163
2,771
kWh
|
$72
-
kW-mo/yr
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $222 | $363 |
$150
2,534
kWh
|
$72
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $50,771 | $128,049 |
$41,111
696,806
kWh
|
$5,890
-
kW-mo/yr
|
$3,770 | ||
| TOTAL IMPLEMENTED | $4,554 | $17,638 |
$368
6,238
kWh
|
$416
-
kW-mo/yr
|
$3,770 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs