ITAC Assessment: UD0329
ITAC logo
ITAC Assessment: UD0329
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product PLASTIC AUTO COMPONENTS
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area
n/a
Annual Production 6,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $321,275 6,712,485
kWh
Natural Gas $28,694 6,134
MMBtu
Other Energy $1,256 1,256
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,238 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,238

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.3212: Optimize plant power factor $17,856 $20,000 $17,856
-
kWh
- -
02 2.2437: Recover waste heat from equipment $5,309 $1,000 - $5,309
-
MMBtu
-
03 3.6124: Burn waste oil for heat $6,067 - $263
4,396
kWh
$5,804
-
MMBtu
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,783 $7,500 $2,393
60,375
kWh
- $390
05 2.7447: Install vinyl strip / high speed / air curtain doors $1,223 $6,240 - $1,223
-
MMBtu
-
TOTAL RECOMMENDED $33,238 $34,740 $20,512
64,771
kWh
$12,336
-
MMBtu
$390
TOTAL IMPLEMENTED $33,238 $34,740 $20,512
64,771
kWh
$12,336
-
MMBtu
$390
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs