ITAC Assessment: UD0312
ITAC logo
ITAC Assessment: UD0312
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1990
Principal Product VINYL WALL COVERINGS
NAICS
n/a
SIC 2295: Coated Fabrics, Not Rubberized
Sales Range $50
M
to 100
M
# of Employees 514
Plant Area
n/a
Annual Production 127,790,000
thousand feet
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,230,754 27,560,376
kWh
Coal $734,240 440,538
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $305,096 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $42,716

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Coal Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,153 $2,400 $708
17,878
kWh
$(-92.0)
-
MMBtu
$537
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,262 $7,825 $4,604
116,940
kWh
$(-612.0)
-
MMBtu
$270
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,422 $2,000 $2,502
63,599
kWh
- $920
04 2.3212: Optimize plant power factor $157,000 $220,000 $157,000
-
kWh
- -
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $18,569 - $20,569
-
kWh
- $(-2,000.0)
06 2.2441: Preheat boiler makeup water with waste process heat $8,884 - $5,000
111,958
kWh
$3,344
-
MMBtu
$540
07 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $6,775 $5,000 $6,775
213,951
kWh
- -
08 2.7261: Install timers and/or thermostats $21,868 $12,000 - $21,868
-
MMBtu
-
09 2.2135: Repair and eliminate steam leaks $24,995 - - $11,308
-
MMBtu
$13,687
10 2.2414: Use waste heat from hot flue gases to preheat $58,168 $100,000 - $58,168
-
MMBtu
-
TOTAL RECOMMENDED $305,096 $349,225 $197,158
524,326
kWh
$93,984
-
MMBtu
$13,954
TOTAL IMPLEMENTED $42,716 $12,225 $12,814
310,375
kWh
$13,948
-
MMBtu
$15,954
Yearly Savings* Imp'd Cost* Electricity Usage Savings Coal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs