Assessment Year | 1989 |
---|---|
Principal Product | VALVES & PIPE FITTINGS |
NAICS |
n/a
|
SIC | 3494: Valves and Pipe Fittings, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 215 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $236,915 | 5,576,495 |
kWh
|
$0.042 |
Natural Gas | $105,430 | 31,559 |
MMBtu
|
$3.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,949 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,801 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,966 | - |
$4,116
-
kWh
|
- | $(-150.0) | |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,322 | - |
$4,322
-
kWh
|
- | $(-1,000.0) | |
03 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $14,860 | $25,000 |
$7,574
235,346
kWh
|
- | $7,286 | |
04 | 2.6232: Install set-back timers | $3,801 | - |
$3,696
123,095
kWh
|
$(-445.0)
-
MMBtu
|
$550 | |
TOTAL RECOMMENDED | $25,949 | $25,000 |
$19,708
358,441
kWh
|
$(-445.0)
-
MMBtu
|
$6,686 | ||
TOTAL IMPLEMENTED | $3,801 | - |
$3,696
123,095
kWh
|
$(-445.0)
-
MMBtu
|
$550 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs