ITAC Assessment: OR0407
ITAC logo
ITAC Assessment: OR0407
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Leather Boots
NAICS
n/a
SIC 3143: Men's Footwear, Except Athletic
Sales Range $10
M
to 50
M
# of Employees 112
Plant Area 60,000
ft2
Annual Production 194,200
pieces
Production Hrs. Annual 2,040
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $41,253 701,100
kWh
Electricity Demand $14,998 3,132
kW-mo/yr
Electricity Fees $447 -
Natural Gas $9,932 1,055
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $665,988 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $625,026

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Primary Raw Material Savings Primary Product Savings Increase in Production Savings
01 4.111: Add equipment/ operators to reduce production bottleneck $590,625 $155,700 - - - $(-346,875.0) - $937,500
02 4.132: Purchase new equipment to reduce material use / cost $38,835 $19,800 - - $55
-
lb
$38,780 - -
03 4.122: Develop standard procedures to improve internal yields $31,415 $55,000 - - - - $31,415 -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,986 $3,000 $1,990
33,823
kWh
$996
-
kW-mo/yr
- - - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $2,127 - $1,475
27,075
kWh
$652
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $665,988 $233,500 $3,465
60,898
kWh
$1,648
-
kW-mo/yr
$55
-
lb
$(-308,095.0) $31,415 $937,500
TOTAL IMPLEMENTED $625,026 $213,700 $1,990
33,823
kWh
$996
-
kW-mo/yr
- $(-346,875.0) $31,415 $937,500
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs