Assessment Year | 1989 |
---|---|
Principal Product | PRESTRESSED CONCRETE |
NAICS |
n/a
|
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | $5 M to 10M |
# of Employees | 69 |
Plant Area |
n/a
|
Annual Production | 5,000
thousand feet
|
Production Hrs. Annual | 2,200
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $112,857 | 1,549,238 |
kWh
|
$0.073 |
Natural Gas | $95,623 | 23,612 |
MMBtu
|
$4.05 |
Fuel Oil #2 | $11,510 | 2,040 |
MMBtu
|
$5.64 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,054 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,494 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,196 | $700 |
$1,566
40,152
kWh
|
$(-370.0)
-
MMBtu
|
- | - | |
02 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $3,183 | $2,400 |
$3,183
152,989
kWh
|
- | - | - | |
03 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $6,445 | $400 |
$6,445
37,808
kWh
|
- | - | - | |
04 | 2.2437: Recover waste heat from equipment | $941 | $1,000 | - |
$941
-
MMBtu
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $764 | $1,005 |
$765
11,137
kWh
|
$(-51.0)
-
MMBtu
|
- | $50 | |
06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,534 | $2,000 | - |
$4,343
-
MMBtu
|
$441
-
MMBtu
|
$(-250.0) | |
07 | 2.7494: Install storm windows and doors | $4,775 | $2,300 | - |
$4,775
-
MMBtu
|
- | - | |
08 | 2.7261: Install timers and/or thermostats | $3,216 | $600 | - |
$3,216
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $25,054 | $10,405 |
$11,959
242,086
kWh
|
$12,854
-
MMBtu
|
$441
-
MMBtu
|
$(-200.0) | ||
TOTAL IMPLEMENTED | $6,494 | $3,705 |
$2,331
51,289
kWh
|
$3,922
-
MMBtu
|
$441
-
MMBtu
|
$(-200.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs