| Assessment Year | 1989 |
|---|---|
| Principal Product | PRESTRESSED CONCRETE |
| NAICS |
n/a
|
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $5 M to 10M |
| # of Employees | 69 |
| Plant Area |
n/a
|
| Annual Production | 5,000
thousand feet
|
| Production Hrs. Annual | 2,200
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $112,857 | 1,549,238 |
kWh
|
$0.073 |
| Natural Gas | $95,623 | 23,612 |
MMBtu
|
$4.05 |
| Fuel Oil #2 | $11,510 | 2,040 |
MMBtu
|
$5.64 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $25,054 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,494 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,196 | $700 |
$1,566
40,152
kWh
|
$(-370.0)
-
MMBtu
|
- | - | |
| 02 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $3,183 | $2,400 |
$3,183
152,989
kWh
|
- | - | - | |
| 03 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $6,445 | $400 |
$6,445
37,808
kWh
|
- | - | - | |
| 04 | 2.2437: Recover waste heat from equipment | $941 | $1,000 | - |
$941
-
MMBtu
|
- | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $764 | $1,005 |
$765
11,137
kWh
|
$(-51.0)
-
MMBtu
|
- | $50 | |
| 06 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,534 | $2,000 | - |
$4,343
-
MMBtu
|
$441
-
MMBtu
|
$(-250.0) | |
| 07 | 2.7494: Install storm windows and doors | $4,775 | $2,300 | - |
$4,775
-
MMBtu
|
- | - | |
| 08 | 2.7261: Install timers and/or thermostats | $3,216 | $600 | - |
$3,216
-
MMBtu
|
- | - | |
| TOTAL RECOMMENDED | $25,054 | $10,405 |
$11,959
242,086
kWh
|
$12,854
-
MMBtu
|
$441
-
MMBtu
|
$(-200.0) | ||
| TOTAL IMPLEMENTED | $6,494 | $3,705 |
$2,331
51,289
kWh
|
$3,922
-
MMBtu
|
$441
-
MMBtu
|
$(-200.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs