| Assessment Year | 1988 |
|---|---|
| Principal Product | STORAGE EQUIPMENT |
| NAICS |
n/a
|
| SIC | 2542: Office and Store Fixtures, Partitions, Shelving, and Lockers, Except Wood |
| Sales Range | $10 M to 50M |
| # of Employees | 63 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,500
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $70,435 | 902,110 |
kWh
|
$0.078 |
| Natural Gas | $78,193 | 24,391 |
MMBtu
|
$3.21 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $11,539 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,539 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $3,698 | $500 | - |
$3,698
-
MMBtu
|
- | |
| 02 | 2.7261: Install timers and/or thermostats | $2,053 | $250 | - |
$2,053
-
MMBtu
|
- | |
| 03 | 2.7261: Install timers and/or thermostats | $2,413 | $1,125 | - |
$2,413
-
MMBtu
|
- | |
| 04 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $1,165 | $1,500 |
$1,213
48,945
kWh
|
$(-330.0)
-
MMBtu
|
$282 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $746 | $1,500 |
$571
8,206
kWh
|
- | $175 | |
| 06 | 2.7492: Use proper thickness of insulation on building envelope | $1,464 | $5,850 | - |
$1,464
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $11,539 | $10,725 |
$1,784
57,151
kWh
|
$9,298
-
MMBtu
|
$457 | ||
| TOTAL IMPLEMENTED | $11,539 | $10,725 |
$1,784
57,151
kWh
|
$9,298
-
MMBtu
|
$457 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs