Assessment Year | 2004 |
---|---|
Principal Product | Oil Field Equipment |
NAICS | 333132: Oil and Gas Field Machinery and Equipment Manufacturing |
SIC | 3533: Oil and Gas Field Machinery and Equipment |
Sales Range | $5 M to 10M |
# of Employees | 120 |
Plant Area |
60,000
ft2
|
Annual Production | 500
pieces
|
Production Hrs. Annual | 2,080
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $72,052 | 791,886 |
kWh
|
$0.091 |
Electricity Demand | $25,256 | 4,555 |
kW-mo/yr
|
$5.54 |
Electricity Fees | $5,358 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $49,226 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $21,969 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $23,552 | $3,917 |
$22,324
301,109
kWh
|
- | $1,228 | - | |
02 | 2.7134: Use photocell controls | $10,938 | $420 |
$10,368
139,849
kWh
|
- | $570 | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,388 | $4,960 |
$6,055
81,668
kWh
|
- | $333 | - | |
04 | 2.8112: Combine utility meters | $2,825 | $420 | - | - | $2,825 | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $880 | $20 | - |
$546
-
kW-mo/yr
|
$334 | - | |
06 | 2.7135: Install occupancy sensors | $571 | $750 |
$541
7,292
kWh
|
- | $30 | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $507 | $508 |
$222
2,996
kWh
|
- | $12 | $273 | |
08 | 2.8123: Pay utility bills on time | $273 | $30 | - | - | $273 | - | |
09 | 4.611: Begin a practice of predictive / preventative maintenance | $2,500 | $60 | - | - | - | $2,500 | |
10 | 4.611: Begin a practice of predictive / preventative maintenance | $792 | $237 | - | - | - | $792 | |
TOTAL RECOMMENDED | $49,226 | $11,322 |
$39,510
532,914
kWh
|
$546
-
kW-mo/yr
|
$5,605 | $3,565 | ||
TOTAL IMPLEMENTED | $21,969 | $6,965 |
$17,186
231,805
kWh
|
- | $1,218 | $3,565 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs