Assessment Year | 1985 |
---|---|
Principal Product | FIRE HOSES |
NAICS |
n/a
|
SIC | 3052: Rubber and Plastics Hose and Belting |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
n/a
|
Annual Production | 11,000
thousand feet
|
Production Hrs. Annual | 5,760
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $117,529 | 2,123,095 |
kWh
|
$0.055 |
Natural Gas | $65,898 | 10,035 |
MMBtu
|
$6.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $6,656 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,368 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,998 | - |
$1,998
-
kWh
|
- | |
02 | 2.4133: Use most efficient type of electric motors | $323 | $583 |
$323
5,862
kWh
|
- | |
03 | 2.2437: Recover waste heat from equipment | $1,825 | $1,000 | - |
$1,825
-
MMBtu
|
|
04 | 2.2511: Insulate bare equipment | $763 | $448 | - |
$763
-
MMBtu
|
|
05 | 2.2414: Use waste heat from hot flue gases to preheat | $1,290 | $5,000 | - |
$1,290
-
MMBtu
|
|
06 | 2.7261: Install timers and/or thermostats | $457 | $121 |
$79
1,758
kWh
|
$378
-
MMBtu
|
|
TOTAL RECOMMENDED | $6,656 | $7,152 |
$2,400
7,620
kWh
|
$4,256
-
MMBtu
|
||
TOTAL IMPLEMENTED | $3,368 | $2,152 |
$402
7,620
kWh
|
$2,966
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs