ITAC Assessment: UD0174
ITAC logo
ITAC Assessment: UD0174
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product FIRE HOSES
NAICS
n/a
SIC 3052: Rubber and Plastics Hose and Belting
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area
n/a
Annual Production 11,000
thousand feet
Production Hrs. Annual 5,760
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $117,529 2,123,095
kWh
Natural Gas $65,898 10,035
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,656 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,368

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $1,998 - $1,998
-
kWh
-
02 2.4133: Use most efficient type of electric motors $323 $583 $323
5,862
kWh
-
03 2.2437: Recover waste heat from equipment $1,825 $1,000 - $1,825
-
MMBtu
04 2.2511: Insulate bare equipment $763 $448 - $763
-
MMBtu
05 2.2414: Use waste heat from hot flue gases to preheat $1,290 $5,000 - $1,290
-
MMBtu
06 2.7261: Install timers and/or thermostats $457 $121 $79
1,758
kWh
$378
-
MMBtu
TOTAL RECOMMENDED $6,656 $7,152 $2,400
7,620
kWh
$4,256
-
MMBtu
TOTAL IMPLEMENTED $3,368 $2,152 $402
7,620
kWh
$2,966
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs