Assessment Year | 1985 |
---|---|
Principal Product | SCREW MACHINE PRODUCTS |
NAICS |
n/a
|
SIC | 3451: Screw Machine Products |
Sales Range | $5 M to 10M |
# of Employees | 95 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,500
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $83,665 | 1,454,572 |
kWh
|
$0.058 |
Natural Gas | $11,422 | 1,976 |
MMBtu
|
$5.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $5,557 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,116 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.6232: Install set-back timers | $2,610 | $1,000 |
$4,662
171,454
kWh
|
$(-2,052.0)
-
MMBtu
|
|
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $688 | $300 |
$688
(-4,396)
kWh
|
- | |
03 | 2.7492: Use proper thickness of insulation on building envelope | $1,217 | $896 | - |
$1,217
-
MMBtu
|
|
04 | 2.6214: Shut off pilots in standby equipment | $536 | - | - |
$536
-
MMBtu
|
|
05 | 2.6121: Reduce hot water temperature to the minimum required | $506 | - | - |
$506
-
MMBtu
|
|
TOTAL RECOMMENDED | $5,557 | $2,196 |
$5,350
167,058
kWh
|
$207
-
MMBtu
|
||
TOTAL IMPLEMENTED | $3,116 | $1,000 |
$4,662
171,454
kWh
|
$(-1,546.0)
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs