| Assessment Year | 1985 |
|---|---|
| Principal Product | SCREW MACHINE PRODUCTS |
| NAICS |
n/a
|
| SIC | 3451: Screw Machine Products |
| Sales Range | $5 M to 10M |
| # of Employees | 95 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,500
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $83,665 | 1,454,572 |
kWh
|
$0.058 |
| Natural Gas | $11,422 | 1,976 |
MMBtu
|
$5.78 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $5,557 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,116 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.6232: Install set-back timers | $2,610 | $1,000 |
$4,662
171,454
kWh
|
$(-2,052.0)
-
MMBtu
|
|
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $688 | $300 |
$688
(-4,396)
kWh
|
- | |
| 03 | 2.7492: Use proper thickness of insulation on building envelope | $1,217 | $896 | - |
$1,217
-
MMBtu
|
|
| 04 | 2.6214: Shut off pilots in standby equipment | $536 | - | - |
$536
-
MMBtu
|
|
| 05 | 2.6121: Reduce hot water temperature to the minimum required | $506 | - | - |
$506
-
MMBtu
|
|
| TOTAL RECOMMENDED | $5,557 | $2,196 |
$5,350
167,058
kWh
|
$207
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $3,116 | $1,000 |
$4,662
171,454
kWh
|
$(-1,546.0)
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs