| Assessment Year | 1984 |
|---|---|
| Principal Product | PAPER BOARD |
| NAICS |
n/a
|
| SIC | 2631: Paperboard Mills |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
n/a
|
| Annual Production | 40,500
ton
|
| Production Hrs. Annual | 6,374
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $834,593 | 15,645,076 |
kWh
|
$0.053 |
| Natural Gas | $108,176 | 18,651 |
MMBtu
|
$5.80 |
| Fuel Oil #6 | $1,432,898 | 302,480 |
MMBtu
|
$4.74 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $269,582 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $71,081 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #6 Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2136: Install / repair insulation on steam lines | $12,421 | $3,300 | - |
$12,421
-
MMBtu
|
|
| 02 | 2.2425: Use flue gases to heat process or service water | $152,310 | $140,000 |
$(-15,122.0)
(-360,492)
kWh
|
$167,432
-
MMBtu
|
|
| 03 | 2.4131: Size electric motors for peak operating efficiency | $8,600 | $20,000 |
$8,600
279,015
kWh
|
- | |
| 04 | 2.6232: Install set-back timers | $4,080 | $770 |
$4,539
101,407
kWh
|
$(-459.0)
-
MMBtu
|
|
| 05 | 2.6222: Use drying oven (batch type) on alternate days or other optimum schedule to run equipment with full loads | $54,580 | - |
$3,917
146,249
kWh
|
$50,663
-
MMBtu
|
|
| 06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $37,591 | - |
$37,591
-
kWh
|
- | |
| TOTAL RECOMMENDED | $269,582 | $164,070 |
$39,525
166,179
kWh
|
$230,057
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $71,081 | $4,070 |
$8,456
247,656
kWh
|
$62,625
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #6 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs