Assessment Year | 1984 |
---|---|
Principal Product | LUMBER-SAWMILL OPERATION |
NAICS |
n/a
|
SIC | 2426: Hardwood Dimension and Flooring Mills |
Sales Range | $1 M to 5M |
# of Employees | 53 |
Plant Area |
n/a
|
Annual Production | 2,490
thousand feet
|
Production Hrs. Annual | 0
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $50,500 | 1,000,000 |
kWh
|
$0.051 |
Natural Gas | $2,486 | 430 |
MMBtu
|
$5.78 |
Wood | $38,400 | 33,024 |
MMBtu
|
$1.16 |
Other Energy | $161,606 | 42,530 |
MMBtu
|
$3.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,945 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,383 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Wood Savings | Other Energy Savings |
---|---|---|---|---|---|---|---|
01 | 2.2515: Use optimum thickness insulation | $5,281 | $5,000 | - | - |
$5,281
-
MMBtu
|
|
02 | 2.2515: Use optimum thickness insulation | $19,560 | $40,500 | - | - |
$19,560
-
MMBtu
|
|
03 | 2.6232: Install set-back timers | $1,754 | $1,271 |
$1,754
38,687
kWh
|
- | - | |
04 | 2.1392: Replace purchased steam with other energy source | $3,629 | $6,000 | - |
$(-5,760.0)
-
MMBtu
|
$9,389
-
MMBtu
|
|
05 | 2.2191: Substitute hot process fluids for steam | $1,721 | $3,000 | - | - |
$1,721
-
MMBtu
|
|
TOTAL RECOMMENDED | $31,945 | $55,771 |
$1,754
38,687
kWh
|
$(-5,760.0)
-
MMBtu
|
$35,951
-
MMBtu
|
||
TOTAL IMPLEMENTED | $5,383 | $7,271 |
$1,754
38,687
kWh
|
$(-5,760.0)
-
MMBtu
|
$9,389
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs