| Assessment Year | 1984 |
|---|---|
| Principal Product | AUTOMOTIVE TRIM |
| NAICS |
n/a
|
| SIC | 3465: Automotive Stampings |
| Sales Range | $10 M to 50M |
| # of Employees | 190 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $197,134 | 3,005,276 |
kWh
|
$0.066 |
| Natural Gas | $204,292 | 36,583 |
MMBtu
|
$5.58 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $36,587 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $36,587 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $7,171 | - |
$7,171
9,086
kWh
|
- | |
| 02 | 2.7421: Reduce glazed areas in buildings | $17,464 | $50,000 | - |
$17,464
-
MMBtu
|
|
| 03 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $3,070 | $8,000 |
$3,070
30,774
kWh
|
- | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $1,853 | $800 |
$1,853
29,015
kWh
|
- | |
| 05 | 2.2444: Use hot process fluids to preheat incoming process fluids | $2,576 | $4,000 | - |
$2,576
-
MMBtu
|
|
| 06 | 2.2414: Use waste heat from hot flue gases to preheat | $4,453 | $20,000 | - |
$4,453
-
MMBtu
|
|
| TOTAL RECOMMENDED | $36,587 | $82,800 |
$12,094
68,875
kWh
|
$24,493
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $36,587 | $82,800 |
$12,094
68,875
kWh
|
$24,493
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs