Assessment Year | 1983 |
---|---|
Principal Product | ROPES AND TWINES |
NAICS |
n/a
|
SIC | 2298: Cordage and Twine |
Sales Range | $10 M to 50M |
# of Employees | 170 |
Plant Area |
n/a
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,900
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $173,012 | 2,864,303 |
kWh
|
$0.060 |
Natural Gas | $157,872 | 28,162 |
MMBtu
|
$5.61 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $73,278 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $57,310 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2136: Install / repair insulation on steam lines | $4,597 | $980 | - |
$4,597
-
MMBtu
|
|
02 | 2.2511: Insulate bare equipment | $9,554 | $600 |
$9,554
135,404
kWh
|
- | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $12,630 | $800 | - |
$12,630
-
MMBtu
|
|
04 | 2.2414: Use waste heat from hot flue gases to preheat | $16,051 | $40,000 |
$(-3,534.0)
(-50,117)
kWh
|
$19,585
-
MMBtu
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,827 | $6,843 |
$9,686
145,369
kWh
|
$(-1,859.0)
-
MMBtu
|
|
06 | 2.7492: Use proper thickness of insulation on building envelope | $15,968 | $61,880 | - |
$15,968
-
MMBtu
|
|
07 | 2.7441: Replace broken windows and/or window sash | $6,651 | $5,475 | - |
$6,651
-
MMBtu
|
|
TOTAL RECOMMENDED | $73,278 | $116,578 |
$15,706
230,656
kWh
|
$57,572
-
MMBtu
|
||
TOTAL IMPLEMENTED | $57,310 | $54,698 |
$15,706
230,656
kWh
|
$41,604
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs