Assessment Year | 2025 |
---|---|
Principal Product | Aircraft parts |
NAICS | 336411: Aircraft Manufacturing |
SIC | 3721: Aircraft |
Sales Range | $50 M to 100M |
# of Employees | 253 |
Plant Area |
189,080
ft2
|
Annual Production | 295,470
units
|
Production Hrs. Annual | 6,214
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $437,367 | 2,320,956 |
kWh
|
$0.19 |
Electricity Demand | $89,512 | 4,956 |
kW-mo/yr
|
$18.06 |
Electricity Fees | $67,727 | - |
|
- |
Natural Gas | $253,474 | 34,087 |
MMBtu
|
$7.44 |
TOTAL YEARLY COSTS | $848,079 | |||
RECOMMENDED SAVINGS* | $263,673 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.8123: Pay utility bills on time | $5,770 | - | - | - | - | $5,770 | |
02 | 2.8114: Change rate schedules or other changes in utility service | $107,691 | - | - | - | - | $107,691 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,996 | $3,315 |
$2,908
15,434
kWh
|
$88
-
kW-mo/yr
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,740 | $150 |
$6,564
35,045
kWh
|
$1,176
-
kW-mo/yr
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $42 | $57 |
$37
197
kWh
|
$5
-
kW-mo/yr
|
- | - | |
06 | 2.7229: Air condition only space necessary | $68 | - |
$68
360
kWh
|
- | - | - | |
07 | 2.2511: Insulate bare equipment | $579 | $464 | - | - |
$579
-
MMBtu
|
- | |
08 | 2.7232: Replace existing hvac unit with high efficiency model | $46,365 | $258,963 |
$45,874
243,490
kWh
|
$491
-
kW-mo/yr
|
- | - | |
09 | 2.9114: Use solar heat to make electricty | $90,908 | $710,557 |
$90,908
482,526
kWh
|
- | - | - | |
10 | 2.6218: Turn off equipment when not in use | $1,049 | - |
$926
4,913
kWh
|
$123
-
kW-mo/yr
|
- | - | |
11 | 2.2511: Insulate bare equipment | $467 | $505 | - | - |
$467
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $263,673 | $974,011 |
$147,284
781,965
kWh
|
$1,883
-
kW-mo/yr
|
$1,046
-
MMBtu
|
$113,460 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs