ITAC Assessment: UC2419
ITAC logo
ITAC Assessment: UC2419
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Petroleum additives
NAICS 325199: All Other Basic Organic Chemical Manufacturing
SIC 2869: Industrial Organic Chemicals, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 30
Plant Area 71,600
ft2
Annual Production 8,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $158,511 2,101,200
kWh
Electricity Demand $100,634 5,249
kW-mo/yr
Electricity Fees $26,332 -
Natural Gas $427,150 35,956
MMBtu
Waste Disposal Costs
Water Usage $78,434 2,027
Tgal
TOTAL YEARLY COSTS $791,061
RECOMMENDED SAVINGS* $109,767 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
01 2.8121: Apply for tax-free status for energy purchases $15,596 - - - - - $15,596
02 2.8123: Pay utility bills on time $178 - - - - - $178
03 2.3212: Optimize plant power factor $6,548 $10,295 - - $6,548 - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,510 $2,929 $1,563
20,773
kWh
$947
-
kW-mo/yr
- - -
05 2.2136: Install / repair insulation on steam lines $7,234 $1,183 - - - $7,234
-
MMBtu
-
06 2.2511: Insulate bare equipment $22,646 $4,752 - - - $22,646
-
MMBtu
-
07 2.7261: Install timers and/or thermostats $149 $390 - - - $149
-
MMBtu
-
08 2.4231: Reduce the pressure of compressed air to the minimum required $436 $75 $419
5,553
kWh
$17
-
kW-mo/yr
- - -
09 2.9114: Use solar heat to make electricty $54,471 $776,252 $54,471
722,423
kWh
- - - -
TOTAL RECOMMENDED $109,767 $795,876 $56,453
748,748
kWh
$964
-
kW-mo/yr
$6,548 $30,029
-
MMBtu
$15,774
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs