| Assessment Year | 2025 |
|---|---|
| Principal Product | Petroleum additives |
| NAICS | 325199: All Other Basic Organic Chemical Manufacturing |
| SIC | 2869: Industrial Organic Chemicals, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 30 |
| Plant Area |
71,600
ft2
|
| Annual Production | 8,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $158,511 | 2,101,200 |
kWh
|
$0.075 | |
| Electricity Demand | $100,634 | 5,249 |
kW-mo/yr
|
$19.17 | |
| Electricity Fees | $26,332 | - |
|
- | |
| Natural Gas | $427,150 | 35,956 |
MMBtu
|
$11.88 | |
| Waste Disposal Costs | |||||
| Water Usage | $78,434 | 2,027 |
Tgal
|
$38.69 | |
| TOTAL YEARLY COSTS | $791,061 | ||||
| RECOMMENDED SAVINGS* | $109,767 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $15,596 | - | - | - | - | - | $15,596 | |
| 02 | 2.8123: Pay utility bills on time | $178 | - | - | - | - | - | $178 | |
| 03 | 2.3212: Optimize plant power factor | $6,548 | $10,295 | - | - | $6,548 | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,510 | $2,929 |
$1,563
20,773
kWh
|
$947
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.2136: Install / repair insulation on steam lines | $7,234 | $1,183 | - | - | - |
$7,234
-
MMBtu
|
- | |
| 06 | 2.2511: Insulate bare equipment | $22,646 | $4,752 | - | - | - |
$22,646
-
MMBtu
|
- | |
| 07 | 2.7261: Install timers and/or thermostats | $149 | $390 | - | - | - |
$149
-
MMBtu
|
- | |
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $436 | $75 |
$419
5,553
kWh
|
$17
-
kW-mo/yr
|
- | - | - | |
| 09 | 2.9114: Use solar heat to make electricty | $54,471 | $776,252 |
$54,471
722,423
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $109,767 | $795,876 |
$56,453
748,748
kWh
|
$964
-
kW-mo/yr
|
$6,548 |
$30,029
-
MMBtu
|
$15,774 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs