ITAC Assessment: UC2418
ITAC logo
ITAC Assessment: UC2418
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Paint related chemicals
NAICS 325510: Paint and Coating Manufacturing
SIC 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 49
Plant Area 129,508
ft2
Annual Production 327,229
units
Production Hrs. Annual 2,850
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $94,960 614,148
kWh
Electricity Demand $58,431 2,210
kW-mo/yr
Electricity Fees $14,562 -
Natural Gas $18,417 1,866
MMBtu
TOTAL YEARLY COSTS $186,371
RECOMMENDED SAVINGS* $46,887 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.8121: Apply for tax-free status for energy purchases $12,058 - - - - $12,058 - -
02 2.3212: Optimize plant power factor $7,122 $100 - - - - - $7,122
03 2.9114: Use solar heat to make electricty $15,270 $240,764 $17,643
117,620
kWh
- - - $(-2,372.5) -
04 2.3141: Use battery storage for demand control $11,473 $61,975 $(-3,964.4)
(-26,429)
kWh
$15,864
-
kW-mo/yr
$(-426.6) - - -
05 2.6231: Utilize controls to operate equipment only when needed $964 $30 $964
6,427
kWh
- - - - -
TOTAL RECOMMENDED $46,887 $302,870 $14,643
97,617
kWh
$15,864
-
kW-mo/yr
$(-426.6) $12,058 $(-2,372.5) $7,122
TOTAL IMPLEMENTED - - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs