| Assessment Year | 2012 |
|---|---|
| Principal Product | Rooftop Membranes |
| NAICS | 326113: Unlaminated Plastics Film and Sheet (except Packaging) Manufacturing |
| SIC | 3081: Unsupported Plastics Film and Sheet |
| Sales Range | $10 M to 50M |
| # of Employees | 12 |
| Plant Area |
245,000
ft2
|
| Annual Production | 10,000
ton
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Pennsylvania |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $964,175 | 12,807,000 |
kWh
|
$0.075 |
| Electricity Demand | $6,840 | 27,791 |
kW-mo/yr
|
$0.25 |
| Natural Gas | $314,371 | 40,943 |
MMBtu
|
$7.68 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $248,546 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $50,414 | $67,000 |
$50,124
668,321
kWh
|
$290
-
kW-mo/yr
|
- | |
| 02 | 2.2622: Replace existing chiller with high efficiency model | $167,678 | $90,000 |
$166,752
2,223,360
kWh
|
$926
-
kW-mo/yr
|
- | |
| 03 | 2.2113: Repair or replace steam traps | $14,506 | $4,200 | - | - |
$14,506
-
MMBtu
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,536 | $1,000 |
$4,511
60,148
kWh
|
$25
-
kW-mo/yr
|
- | |
| 05 | 2.7425: Clean or color roof to reduce solar load | $1,380 | $6,630 |
$1,380
18,393
kWh
|
- | - | |
| 06 | 2.2442: Preheat combustion air with waste heat | $3,932 | $6,000 | - | - |
$3,932
-
MMBtu
|
|
| 07 | 2.1233: Analyze flue gas for proper air/fuel ratio | $6,100 | $16,000 | - | - |
$6,100
-
MMBtu
|
|
| TOTAL RECOMMENDED | $248,546 | $190,830 |
$222,767
2,970,222
kWh
|
$1,241
-
kW-mo/yr
|
$24,538
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs