Assessment Year | 2008 |
---|---|
Principal Product | Folding cartons |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2759: Commercial Printing, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 43 |
Plant Area |
150,000
ft2
|
Annual Production | 600
ton
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $157,294 | 1,266,184 |
kWh
|
$0.12 |
Electricity Demand | $63,278 | 5,941 |
kW-mo/yr
|
$10.65 |
Electricity Fees | $8,883 | - |
|
- |
Natural Gas | $30,158 | 1,991 |
MMBtu
|
$15.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,703 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,551 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,404 | $14,500 |
$11,114
89,485
kWh
|
$2,290
-
kW-mo/yr
|
- | |
02 | 2.7243: Improve air circulation with destratification fans / other methods | $5,185 | $17,080 |
$(-2,437.0)
(-19,622)
kWh
|
$(-288.0)
-
kW-mo/yr
|
$7,910
-
MMBtu
|
|
03 | 2.7229: Air condition only space necessary | $4,818 | $19,300 |
$633
5,100
kWh
|
- |
$4,185
-
MMBtu
|
|
04 | 2.2437: Recover waste heat from equipment | $3,265 | $4,100 | - | - |
$3,265
-
MMBtu
|
|
05 | 2.7314: Reduce ventilation air | $2,499 | $9,000 |
$108
866
kWh
|
- |
$2,391
-
MMBtu
|
|
06 | 2.5121: Redesign flow to minimize mass transfer length | $2,149 | $11,000 |
$2,149
17,300
kWh
|
- | - | |
07 | 2.2511: Insulate bare equipment | $383 | $650 | - | - |
$383
-
MMBtu
|
|
TOTAL RECOMMENDED | $31,703 | $75,630 |
$11,567
93,129
kWh
|
$2,002
-
kW-mo/yr
|
$18,134
-
MMBtu
|
||
TOTAL IMPLEMENTED | $19,551 | $28,250 |
$11,222
90,351
kWh
|
$2,290
-
kW-mo/yr
|
$6,039
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs