ITAC Assessment: UC2414
ITAC logo
ITAC Assessment: UC2414
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Soft drink
NAICS 312111: Soft Drink Manufacturing
SIC 2087: Flavoring Extracts and Flavoring Syrups, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 25
Plant Area 35,500
ft2
Annual Production 3,000,000
units
Production Hrs. Annual 4,000
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $31,553 301,269
kWh
Electricity Demand $29,360 1,790
kW-mo/yr
Electricity Fees $4,749 -
Natural Gas $24,719 1,765
MMBtu
Waste Disposal Costs
Water Usage $21,074 2,390
Tgal
TOTAL YEARLY COSTS $111,454
RECOMMENDED SAVINGS* $7,662 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.8121: Apply for tax-free status for energy purchases $1,657 - - - - $1,657 -
02 2.7135: Install occupancy sensors $815 $693 $771
7,360
kWh
$44
-
kW-mo/yr
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $580 $75 $397
3,793
kWh
$183
-
kW-mo/yr
- - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $539 $1,300 $369
3,526
kWh
$170
-
kW-mo/yr
- - -
05 2.4221: Install compressor air intakes in coolest locations $225 $1,283 $154
1,468
kWh
$71
-
kW-mo/yr
- - -
06 2.2437: Recover waste heat from equipment $2,784 $5,236 $1,095
10,460
kWh
$504
-
kW-mo/yr
$1,184
-
MMBtu
- -
07 4.652: Replace existing equipment with more suitable substitutes $1,063 $4,891 $964
9,204
kWh
$17
-
kW-mo/yr
- - $82
TOTAL RECOMMENDED $7,662 $13,478 $3,749
35,810
kWh
$990
-
kW-mo/yr
$1,184
-
MMBtu
$1,657 $82
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs