Assessment Year | 2024 |
---|---|
Principal Product | Soft drink |
NAICS | 312111: Soft Drink Manufacturing |
SIC | 2087: Flavoring Extracts and Flavoring Syrups, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 25 |
Plant Area |
35,500
ft2
|
Annual Production | 3,000,000
units
|
Production Hrs. Annual | 4,000
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $31,553 | 301,269 |
kWh
|
$0.10 | |
Electricity Demand | $29,360 | 1,790 |
kW-mo/yr
|
$16.40 | |
Electricity Fees | $4,749 | - |
|
- | |
Natural Gas | $24,719 | 1,765 |
MMBtu
|
$14.00 | |
Waste Disposal Costs | |||||
Water Usage | $21,074 | 2,390 |
Tgal
|
$8.82 | |
TOTAL YEARLY COSTS | $111,454 | ||||
RECOMMENDED SAVINGS* | $7,662 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $1,657 | - | - | - | - | $1,657 | - | |
02 | 2.7135: Install occupancy sensors | $815 | $693 |
$771
7,360
kWh
|
$44
-
kW-mo/yr
|
- | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $580 | $75 |
$397
3,793
kWh
|
$183
-
kW-mo/yr
|
- | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $539 | $1,300 |
$369
3,526
kWh
|
$170
-
kW-mo/yr
|
- | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $225 | $1,283 |
$154
1,468
kWh
|
$71
-
kW-mo/yr
|
- | - | - | |
06 | 2.2437: Recover waste heat from equipment | $2,784 | $5,236 |
$1,095
10,460
kWh
|
$504
-
kW-mo/yr
|
$1,184
-
MMBtu
|
- | - | |
07 | 4.652: Replace existing equipment with more suitable substitutes | $1,063 | $4,891 |
$964
9,204
kWh
|
$17
-
kW-mo/yr
|
- | - | $82 | |
TOTAL RECOMMENDED | $7,662 | $13,478 |
$3,749
35,810
kWh
|
$990
-
kW-mo/yr
|
$1,184
-
MMBtu
|
$1,657 | $82 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs