Assessment Year | 2024 |
---|---|
Principal Product | Printed circuit boards |
NAICS | 334418: Printed Circuit Assembly (Electronic Assembly) Manufacturing |
SIC | 3679: Electronic Components, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 60 |
Plant Area |
35,000
ft2
|
Annual Production | 100,000
units
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $49,509 | 557,728 |
kWh
|
$0.089 |
Electricity Demand | $33,659 | 2,196 |
kW-mo/yr
|
$15.33 |
Electricity Fees | $6,376 | - |
|
- |
Natural Gas | $15,674 | 1,353 |
MMBtu
|
$11.58 |
TOTAL YEARLY COSTS | $105,218 | |||
RECOMMENDED SAVINGS* | $27,967 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $962 | - | - | - | $962 | - | - | |
02 | 2.6212: Turn off equipment during breaks, reduce operating time | $78 | $100 |
$78
884
kWh
|
- | - | - | - | |
03 | 2.9114: Use solar heat to make electricty | $23,268 | $223,076 |
$27,127
305,484
kWh
|
- | - | - | $(-3,859.0) | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,065 | $75 |
$861
9,697
kWh
|
$204
-
kW-mo/yr
|
- | - | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $572 | $2,608 |
$572
6,439
kWh
|
- | - | - | - | |
06 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $1,203 | $1,779 |
$833
9,376
kWh
|
$370
-
kW-mo/yr
|
- | - | - | |
07 | 2.7261: Install timers and/or thermostats | $819 | $3,620 |
$73
819
kWh
|
- | - |
$747
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $27,967 | $231,258 |
$29,544
332,698
kWh
|
$574
-
kW-mo/yr
|
$962 |
$747
-
MMBtu
|
$(-3,859.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs