ITAC Assessment: UC2316
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Medical devices
NAICS 339112: Surgical and Medical Instrument Manufacturing
SIC 3841: Surgical and Medical Instruments and Apparatus
Sales Range $10
M
to 50
M
# of Employees 460
Plant Area 385,000
ft2
Annual Production 2,500,000,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,574,836 35,935,625
kWh
Electricity Demand $1,015,900 59,122
kW-mo/yr
Electricity Fees $(-56,453.4) -
Fuel Oil #2 $280,078 10,885
MMBtu
TOTAL YEARLY COSTS $3,814,361
RECOMMENDED SAVINGS* $1,881,119 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Fuel Oil #2 Savings Ancillary Material Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $26,355 $75 $19,842
276,734
kWh
$6,513
-
kW-mo/yr
- - -
02 2.6231: Utilize controls to operate equipment only when needed $7,167 $5,801 $5,396
75,252
kWh
$1,771
-
kW-mo/yr
- - -
03 3.5311: Recover and reuse waste material $76,811 $332,613 $(-431.5)
(-6,018)
kWh
$(-3,432.6)
-
kW-mo/yr
- $93,326
-
MMBtu
$(-12,650.9)
04 2.1222: Install turbulators $13,337 $10,920 - - - $13,337
-
MMBtu
-
05 2.1241: Reduce excessive boiler blowdown $2,801 $12,000 - - - $2,801
-
MMBtu
-
06 2.1331: Burn a less expensive grade of fuel $153,910 $207,578 - - $(-126,168.0)
-
MMBtu
$280,078
-
MMBtu
-
07 2.1224: Replace boiler $177,614 $423,535 - - $(-102,464.0)
-
MMBtu
$280,078
-
MMBtu
-
08 2.3413: Burn fossil fuel to produce steam to drive a steam turbine-generator and use steam exhaust for heat $22,194 $134,412 $20,511
286,065
kWh
$1,683
-
kW-mo/yr
- - -
09 2.9121: Install wind powered electric generator $1,380,736 $10,992,131 $1,380,736
19,257,128
kWh
- - - -
10 2.9114: Use solar heat to make electricty $20,195 $268,543 $20,195
281,653
kWh
- - - -
TOTAL RECOMMENDED $1,881,119 $12,387,607 $1,446,247
20,170,814
kWh
$6,534
-
kW-mo/yr
$(-228,632.0)
-
MMBtu
$669,620
-
MMBtu
$(-12,650.9)
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Fuel Oil #2 Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs