ITAC Assessment: UC2311
ITAC logo
ITAC Assessment: UC2311
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Wood products
NAICS 321113: Sawmills
SIC 2421: Sawmills and Planing Mills, General
Sales Range $10
M
to 50
M
# of Employees 80
Plant Area 2,500,000
ft2
Annual Production 11,000
thousand feet
Production Hrs. Annual 2,100
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $150,426 2,183,424
kWh
Electricity Demand $203,272 8,501
kW-mo/yr
Electricity Fees $46,309 -
LPG $7,957 372
MMBtu
Fuel Oil #2 $280,087 10,309
MMBtu
Other Gas $27,577 1,217
MMBtu
Other Energy $8,795 252
MMBtu
TOTAL YEARLY COSTS $724,422
RECOMMENDED SAVINGS* $230,973 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $71,402

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Fuel Oil #2 Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.8123: Pay utility bills on time $287 - - - $287 - - -
02 2.3212: Optimize plant power factor $48,394 $1,010 - - $48,394 - - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,309 $1,900 $1,565
22,714
kWh
$744
-
kW-mo/yr
- - - -
04 2.6218: Turn off equipment when not in use $9,913 $75 $6,718
97,518
kWh
$3,194
-
kW-mo/yr
- - - -
05 2.4221: Install compressor air intakes in coolest locations $830 $428 $563
8,165
kWh
$267
-
kW-mo/yr
- - - -
06 2.4239: Eliminate or reduce compressed air usage $215 $100 $215
3,115
kWh
- - - - -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $312 - $182
2,638
kWh
$180
-
kW-mo/yr
- - - $(-50.0)
08 2.1222: Install turbulators $18,806 $5,970 - - - $18,806
-
MMBtu
- -
09 2.2136: Install / repair insulation on steam lines $3,022 $4,212 - - - $3,022
-
MMBtu
- -
10 2.2135: Repair and eliminate steam leaks $2,564 $1,995 - - - $2,564
-
MMBtu
- -
11 2.7142: Utilize higher efficiency lamps and/or ballasts $4,083 $4,561 $1,524
22,123
kWh
$2,539
-
kW-mo/yr
- - $37 $(-18.3)
12 2.9114: Use solar heat to make electricty $95,417 $1,401,053 $118,194
1,715,440
kWh
- - - $(-22,776.6) -
13 2.3141: Use battery storage for demand control $44,822 $159,957 $(-4,402.1)
(-63,890)
kWh
$51,646
-
kW-mo/yr
- - $(-2,421.4) -
TOTAL RECOMMENDED $230,973 $1,581,260 $124,558
1,807,824
kWh
$58,571
-
kW-mo/yr
$48,681 $24,391
-
MMBtu
$(-25,160.7) $(-68.3)
TOTAL IMPLEMENTED $71,402 $14,180 $10,370
150,520
kWh
$6,745
-
kW-mo/yr
$48,681 $5,586
-
MMBtu
$37 $(-18.3)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Fuel Oil #2 Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs