Assessment Year | 2023 |
---|---|
Principal Product | Wood products |
NAICS | 321113: Sawmills |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
2,500,000
ft2
|
Annual Production | 11,000
thousand feet
|
Production Hrs. Annual | 2,100
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $150,426 | 2,183,424 |
kWh
|
$0.069 |
Electricity Demand | $203,272 | 8,501 |
kW-mo/yr
|
$23.91 |
Electricity Fees | $46,309 | - |
|
- |
LPG | $7,957 | 372 |
MMBtu
|
$21.39 |
Fuel Oil #2 | $280,087 | 10,309 |
MMBtu
|
$27.17 |
Other Gas | $27,577 | 1,217 |
MMBtu
|
$22.67 |
Other Energy | $8,795 | 252 |
MMBtu
|
$34.90 |
TOTAL YEARLY COSTS | $724,422 | |||
RECOMMENDED SAVINGS* | $230,973 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $71,402 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #2 Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8123: Pay utility bills on time | $287 | - | - | - | $287 | - | - | - | |
02 | 2.3212: Optimize plant power factor | $48,394 | $1,010 | - | - | $48,394 | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,309 | $1,900 |
$1,565
22,714
kWh
|
$744
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.6218: Turn off equipment when not in use | $9,913 | $75 |
$6,718
97,518
kWh
|
$3,194
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $830 | $428 |
$563
8,165
kWh
|
$267
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4239: Eliminate or reduce compressed air usage | $215 | $100 |
$215
3,115
kWh
|
- | - | - | - | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $312 | - |
$182
2,638
kWh
|
$180
-
kW-mo/yr
|
- | - | - | $(-50.0) | |
08 | 2.1222: Install turbulators | $18,806 | $5,970 | - | - | - |
$18,806
-
MMBtu
|
- | - | |
09 | 2.2136: Install / repair insulation on steam lines | $3,022 | $4,212 | - | - | - |
$3,022
-
MMBtu
|
- | - | |
10 | 2.2135: Repair and eliminate steam leaks | $2,564 | $1,995 | - | - | - |
$2,564
-
MMBtu
|
- | - | |
11 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,083 | $4,561 |
$1,524
22,123
kWh
|
$2,539
-
kW-mo/yr
|
- | - | $37 | $(-18.3) | |
12 | 2.9114: Use solar heat to make electricty | $95,417 | $1,401,053 |
$118,194
1,715,440
kWh
|
- | - | - | $(-22,776.6) | - | |
13 | 2.3141: Use battery storage for demand control | $44,822 | $159,957 |
$(-4,402.1)
(-63,890)
kWh
|
$51,646
-
kW-mo/yr
|
- | - | $(-2,421.4) | - | |
TOTAL RECOMMENDED | $230,973 | $1,581,260 |
$124,558
1,807,824
kWh
|
$58,571
-
kW-mo/yr
|
$48,681 |
$24,391
-
MMBtu
|
$(-25,160.7) | $(-68.3) | ||
TOTAL IMPLEMENTED | $71,402 | $14,180 |
$10,370
150,520
kWh
|
$6,745
-
kW-mo/yr
|
$48,681 |
$5,586
-
MMBtu
|
$37 | $(-18.3) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Fuel Oil #2 Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs