| Assessment Year | 2023 |
|---|---|
| Principal Product | Steel frames |
| NAICS | 332312: Fabricated Structural Metal Manufacturing |
| SIC | 3441: Fabricated Structural Metal |
| Sales Range | $50 M to 100M |
| # of Employees | 61 |
| Plant Area |
125,000
ft2
|
| Annual Production | 8,000
ton
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $149,474 | 1,043,280 |
kWh
|
$0.14 |
| Electricity Demand | $69,676 | 4,836 |
kW-mo/yr
|
$14.41 |
| Electricity Fees | $16,064 | - |
|
- |
| Natural Gas | $65,879 | 6,292 |
MMBtu
|
$10.47 |
| TOTAL YEARLY COSTS | $301,094 | |||
| RECOMMENDED SAVINGS* | $145,575 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,182 | $2,800 |
$831
5,800
kWh
|
$351
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7232: Replace existing hvac unit with high efficiency model | $1,346 | $16,122 |
$(-5,293.8)
(-36,950)
kWh
|
$(-729.5)
-
kW-mo/yr
|
$7,370
-
MMBtu
|
- | - | |
| 03 | 2.7235: Install fossil fuel make-up air unit | $38,532 | $50,758 | - | - |
$38,532
-
MMBtu
|
- | - | |
| 04 | 2.7493: Use double or triple glazed windows to maintain higher relative humidity and to reduce heat losses | $17,250 | $148,500 | - | - |
$17,250
-
MMBtu
|
- | - | |
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $4,740 | $26,230 |
$(-1,697.6)
(-11,849)
kWh
|
$(-233.9)
-
kW-mo/yr
|
$6,672
-
MMBtu
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,863 | $2,882 |
$1,740
12,143
kWh
|
$1,050
-
kW-mo/yr
|
- | $45 | $28 | |
| 07 | 2.7135: Install occupancy sensors | $99 | $260 |
$57
401
kWh
|
$35
-
kW-mo/yr
|
- | $3 | $4 | |
| 08 | 2.9114: Use solar heat to make electricty | $79,562 | $411,323 |
$87,787
612,610
kWh
|
- | - | $(-8,225.0) | - | |
| TOTAL RECOMMENDED | $145,575 | $658,875 |
$83,424
582,155
kWh
|
$472
-
kW-mo/yr
|
$69,824
-
MMBtu
|
$(-8,177.0) | $32 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs