Assessment Year | 2023 |
---|---|
Principal Product | Wastewater treatment |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $10 M to 50M |
# of Employees | 19 |
Plant Area |
80,000
ft2
|
Annual Production | 3,285,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $584,490 | 5,392,290 |
kWh
|
$0.11 |
Electricity Demand | $150,083 | 9,765 |
kW-mo/yr
|
$15.37 |
Electricity Fees | $4,378 | - |
|
- |
Fuel Oil #2 | $2,676 | 123 |
MMBtu
|
$21.79 |
TOTAL YEARLY COSTS | $741,627 | |||
RECOMMENDED SAVINGS* | $128,284 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #2 Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.3192: Use fossil fuel powered generator during peak demand periods | $31,115 | - |
$1,268
11,700
kWh
|
$3,996
-
kW-mo/yr
|
$32,500 | - | - | $(-6,649.2) | - | |
02 | 2.6231: Utilize controls to operate equipment only when needed | $4,557 | $1,500 |
$2,880
26,568
kWh
|
$1,677
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.6231: Utilize controls to operate equipment only when needed | $57,154 | $500 |
$47,859
441,504
kWh
|
$9,295
-
kW-mo/yr
|
- | - | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $3,119 | $33,560 |
$2,611
24,090
kWh
|
$507
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.7232: Replace existing hvac unit with high efficiency model | $2,660 | $16,842 |
$552
5,094
kWh
|
$107
-
kW-mo/yr
|
- | - | - | $400 | $1,601 | |
06 | 2.1332: Convert combustion equipment to burn natural gas | $1,713 | $3,300 | - | - | - |
$(-962.8)
-
MMBtu
|
$2,676
-
MMBtu
|
- | - | |
07 | 2.3141: Use battery storage for demand control | $27,967 | $231,837 |
$(-16,598.0)
(-153,118)
kWh
|
$51,597
-
kW-mo/yr
|
- | - | - | $(-7,032.0) | - | |
TOTAL RECOMMENDED | $128,284 | $287,539 |
$38,572
355,838
kWh
|
$67,179
-
kW-mo/yr
|
$32,500 |
$(-962.8)
-
MMBtu
|
$2,676
-
MMBtu
|
$(-13,281.2) | $1,601 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Fuel Oil #2 Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs