Assessment Year | 2001 |
---|---|
Principal Product | Salt |
NAICS |
n/a
|
SIC | 2899: Chemicals and Chemical Preparations, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 185 |
Plant Area |
n/a
|
Annual Production | 2,500,000
ton
|
Production Hrs. Annual | 6,800
hrs
|
Location (State) | Louisiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,338,482 | 24,125,767 |
kWh
|
$0.055 |
Electricity Demand | $389,118 | 69,238 |
kW-mo/yr
|
$5.62 |
Electricity Fees | $73,810 | - |
|
- |
Natural Gas | $62,675 | 10,633 |
MMBtu
|
$5.89 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $133,373 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,684 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7145: Install skylights | $3,305 | $1,737 |
$2,464
44,415
kWh
|
$714
-
kW-mo/yr
|
$127 | - | |
02 | 2.3212: Optimize plant power factor | $113,313 | $117,135 | n/a | - |
$108,955
-
kW-mo/yr
|
$4,358 | - |
03 | 2.2511: Insulate bare equipment | $5,071 | $5,224 | - | - | - |
$5,071
-
MMBtu
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,898 | $660 |
$2,787
50,241
kWh
|
- | $111 | - | |
05 | 2.7134: Use photocell controls | $8,786 | $495 |
$8,448
152,280
kWh
|
- | $338 | - | |
TOTAL RECOMMENDED | $133,373 | $125,251 |
$13,699
246,936
kWh
|
$109,669
-
kW-mo/yr
|
$4,934 |
$5,071
-
MMBtu
|
||
TOTAL IMPLEMENTED | $11,684 | $1,155 |
$11,235
202,521
kWh
|
- | $449 | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs