| Assessment Year | 2013 |
|---|---|
| Principal Product | Cement |
| NAICS | 327310: Cement Manufacturing |
| SIC | 3241: Cement, Hydraulic |
| Sales Range | $100 M to 500M |
| # of Employees | 107 |
| Plant Area |
4,300,000
ft2
|
| Annual Production | 1,000,000
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $7,284,777 | 112,073,496 |
kWh
|
$0.065 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $158,502 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $87,714 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.4224: Upgrade controls on compressors | $65,646 | $30,000 |
$65,646
1,009,932
kWh
|
|
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $29,047 | $800 |
$29,047
446,885
kWh
|
|
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $21,524 | $800 |
$21,524
331,140
kWh
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $20,585 | $18,890 |
$20,585
316,680
kWh
|
|
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $16,558 | $27,390 |
$16,558
254,730
kWh
|
|
| 06 | 2.4224: Upgrade controls on compressors | $5,142 | $300 |
$5,142
79,112
kWh
|
|
| TOTAL RECOMMENDED | $158,502 | $78,180 |
$158,502
2,438,479
kWh
|
||
| TOTAL IMPLEMENTED | $87,714 | $47,880 |
$87,714
1,349,435
kWh
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs