ITAC Assessment: UA3002
ITAC logo
ITAC Assessment: UA3002
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Car Seats
NAICS 336360: Motor Vehicle Seating and Interior Trim Manufacturing
SIC 2531: Public Building and Related Furniture
Sales Range $1
M
to 5
M
# of Employees 202
Plant Area 96,000
ft2
Annual Production 70,000
pieces
Production Hrs. Annual 2,625
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $171,303 1,746,617
kWh
Electricity Demand $35,014 7,365
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $24,292 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.2437: Recover waste heat from equipment $2,042 $4,063 $2,042
33,705
kWh
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,184 $640 $854
14,101
kWh
$330
-
kW-mo/yr
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $258 $600 $218
3,596
kWh
$40
-
kW-mo/yr
04 2.7442: Keep doors and windows shut when not on use $10,623 - $10,623
175,290
kWh
-
05 2.7221: Lower temperature during the winter season and vice-versa $10,185 - $7,545
124,500
kWh
$2,640
-
kW-mo/yr
TOTAL RECOMMENDED $24,292 $5,303 $21,282
351,192
kWh
$3,010
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs