Assessment Year | 1998 |
---|---|
Principal Product | Magnet Wire |
NAICS |
n/a
|
SIC | 3357: Drawing and Insulating of Nonferrous Wire |
Sales Range | $50 M to 100M |
# of Employees | 115 |
Plant Area |
150,000
ft2
|
Annual Production | 35,000,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $417,935 | 19,724,502 |
kWh
|
$0.021 |
Electricity Demand | $184,460 | 35,442 |
kW-mo/yr
|
$5.20 |
Natural Gas | $598,229 | 149,730 |
MMBtu
|
$4.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $392,501 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $312,001 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $3,709 | $120 |
$2,120
100,234
kWh
|
$59
-
kW-mo/yr
|
- | - | $450 | $1,080 | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,492 | $20 |
$1,081
55,393
kWh
|
$411
-
kW-mo/yr
|
- | - | - | - | - | |
03 | 2.2426: Use waste heat from flue gases to heat space conditioning air | $74,500 | $163,800 | - | - |
$74,500
-
MMBtu
|
- | - | - | - | |
04 | 3.5217: Reuse / recycle/ sell paper products | $6,000 | $1,320 | - | - | - |
$6,000
-
lb
|
- | - | - | |
05 | 4.122: Develop standard procedures to improve internal yields | $306,800 | $117,500 | - | - | - | - | - | - | $306,800 | |
TOTAL RECOMMENDED | $392,501 | $282,760 |
$3,201
155,627
kWh
|
$470
-
kW-mo/yr
|
$74,500
-
MMBtu
|
$6,000
-
lb
|
$450 | $1,080 | $306,800 | ||
TOTAL IMPLEMENTED | $312,001 | $117,640 |
$3,201
155,627
kWh
|
$470
-
kW-mo/yr
|
- | - | $450 | $1,080 | $306,800 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs