ITAC Assessment: UL0207
ITAC logo
ITAC Assessment: UL0207
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Magnet Wire
NAICS
n/a
SIC 3357: Drawing and Insulating of Nonferrous Wire
Sales Range $50
M
to 100
M
# of Employees 115
Plant Area 150,000
ft2
Annual Production 35,000,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $417,935 19,724,502
kWh
Electricity Demand $184,460 35,442
kW-mo/yr
Natural Gas $598,229 149,730
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $392,501 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $312,001

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 2.7111: Reduce illumination to minimum necessary levels $3,709 $120 $2,120
100,234
kWh
$59
-
kW-mo/yr
- - $450 $1,080 -
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,492 $20 $1,081
55,393
kWh
$411
-
kW-mo/yr
- - - - -
03 2.2426: Use waste heat from flue gases to heat space conditioning air $74,500 $163,800 - - $74,500
-
MMBtu
- - - -
04 3.5217: Reuse / recycle/ sell paper products $6,000 $1,320 - - - $6,000
-
lb
- - -
05 4.122: Develop standard procedures to improve internal yields $306,800 $117,500 - - - - - - $306,800
TOTAL RECOMMENDED $392,501 $282,760 $3,201
155,627
kWh
$470
-
kW-mo/yr
$74,500
-
MMBtu
$6,000
-
lb
$450 $1,080 $306,800
TOTAL IMPLEMENTED $312,001 $117,640 $3,201
155,627
kWh
$470
-
kW-mo/yr
- - $450 $1,080 $306,800
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs