ITAC Assessment: UA0297
ITAC logo
ITAC Assessment: UA0297
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Wood Kitchen Cabinet
NAICS 337110: Wood Kitchen Cabinet and Countertop Manufacturing
SIC 2434: Wood Kitchen Cabinets
Sales Range $100
M
to 500
M
# of Employees 196
Plant Area 152,000
ft2
Annual Production 338,000
units
Production Hrs. Annual 4,100
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $236,520 3,134,978
kWh
Electricity Demand $158,934 11,911
kW-mo/yr
Electricity Fees $14,046 -
Natural Gas $85,744 70,319
MMBtu
Waste Disposal Costs
Water Usage $6,891 7
Tgal
TOTAL YEARLY COSTS $502,135
RECOMMENDED SAVINGS* $239,817 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.9114: Use solar heat to make electricty $165,904 $2,630,520 $154,636
2,050,874
kWh
$5,580
-
kW-mo/yr
$5,688
02 2.3212: Optimize plant power factor $38,546 $5,696 - - $38,546
03 2.4239: Eliminate or reduce compressed air usage $15,160 $28,210 $7,638
101,300
kWh
$7,002
-
kW-mo/yr
$520
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,778 $7,744 $2,399
31,816
kWh
$1,249
-
kW-mo/yr
$130
05 2.4231: Reduce the pressure of compressed air to the minimum required $3,389 $670 $1,528
20,267
kWh
$1,745
-
kW-mo/yr
$116
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $10,275 $16,734 $6,299
83,548
kWh
$3,624
-
kW-mo/yr
$352
07 2.7261: Install timers and/or thermostats $2,765 $316 $2,670
35,417
kWh
- $95
TOTAL RECOMMENDED $239,817 $2,689,890 $175,170
2,323,222
kWh
$19,200
-
kW-mo/yr
$45,447
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs