ITAC Assessment: UA0294
ITAC logo
ITAC Assessment: UA0294
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Steel materials
NAICS 332312: Fabricated Structural Metal Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 50
Plant Area 132,000
ft2
Annual Production 84,000
units
Production Hrs. Annual 4,000
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $55,467 650,960
kWh
Electricity Demand $50,274 2,530
kW-mo/yr
Electricity Fees $7,166 -
Natural Gas $11,730 1,701
MMBtu
TOTAL YEARLY COSTS $124,637
RECOMMENDED SAVINGS* $71,113 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $232 $250 $74
872
kWh
$143
-
kW-mo/yr
$15
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $813 $1,572 $379
4,446
kWh
$382
-
kW-mo/yr
$52
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $916 $1,133 $580
6,809
kWh
$278
-
kW-mo/yr
$58
04 2.7261: Install timers and/or thermostats $5,323 $29 $4,985
58,511
kWh
- $338
05 2.7135: Install occupancy sensors $2,012 $2,261 $1,884
22,118
kWh
- $128
06 2.9114: Use solar heat to make electricty $46,922 $377,678 $42,703
501,213
kWh
$1,240
-
kW-mo/yr
$2,979
07 2.3212: Optimize plant power factor $14,895 $2,777 - - $14,895
TOTAL RECOMMENDED $71,113 $385,700 $50,605
593,969
kWh
$2,043
-
kW-mo/yr
$18,465
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs