ITAC Assessment: UA0283
ITAC logo
ITAC Assessment: UA0283
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Valves, Fittings
NAICS 332913: Plumbing Fixture Fitting and Trim Manufacturing
SIC 3432: Plumbing Fixture Fittings and Trim
Sales Range $100
M
to 500
M
# of Employees 568
Plant Area 1,061,203
ft2
Annual Production 120,513,270
units
Production Hrs. Annual 6,600
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,631,851 20,334,300
kWh
Electricity Demand $493,982 42,691
kW-mo/yr
Electricity Fees $170,361 -
Natural Gas $198,040 22,039
MMBtu
Waste Disposal Costs
Water Usage $76,497 5,998
Tgal
Water Disposal $64,901 5,998
Tgal
TOTAL YEARLY COSTS $2,635,632
RECOMMENDED SAVINGS* $524,036 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings
01 2.9114: Use solar heat to make electricty $416,153 $3,377,796 $349,887
4,357,254
kWh
$35,404
-
kW-mo/yr
$30,862 - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $24,247 $22,655 $17,786
221,496
kWh
$4,663
-
kW-mo/yr
$1,798 - -
03 2.7135: Install occupancy sensors $4,924 $754 $4,559
56,771
kWh
- $365 - -
04 2.7111: Reduce illumination to minimum necessary levels $4,087 - $2,997
37,319
kWh
$787
-
kW-mo/yr
$303 - -
05 4.821: Pay bills on time to avoid late fees $21,298 - - - $21,298 - -
06 3.4116: Meter recycled water (to reduce sewer charges) $12,662 $6,036 - - - - $12,662
-
Tgal
07 2.7261: Install timers and/or thermostats $14,473 $2,726 $13,400
166,872
kWh
- $1,073 - -
08 2.4231: Reduce the pressure of compressed air to the minimum required $8,686 $750 $4,872
60,671
kWh
$3,170
-
kW-mo/yr
$644 - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,911 $8,591 $5,431
67,638
kWh
$42
-
kW-mo/yr
$438 - -
10 2.4314: Use synthetic lubricant $6,907 $21,930 $5,068
63,109
kWh
$1,327
-
kW-mo/yr
$512 - -
11 2.2414: Use waste heat from hot flue gases to preheat $4,688 $31,108 - - - $4,688
-
MMBtu
-
TOTAL RECOMMENDED $524,036 $3,472,346 $404,000
5,031,130
kWh
$45,393
-
kW-mo/yr
$57,293 $4,688
-
MMBtu
$12,662
-
Tgal
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs