ITAC Assessment: UA0266
ITAC logo
ITAC Assessment: UA0266
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Bread
NAICS 311812: Commercial Bakeries
SIC 2051: Bread and Other Bakery Products, Except Cookies and Crackers
Sales Range $50
M
to 100
M
# of Employees 340
Plant Area 180,000
ft2
Annual Production 105,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $945,652 10,546,664
kWh
Electricity Demand $101,190 25,114
kW-mo/yr
Electricity Fees $46,671 -
Natural Gas $1,096,813 81,987
MMBtu
TOTAL YEARLY COSTS $2,190,326
RECOMMENDED SAVINGS* $62,537 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $19,219 $1,000 $17,287
192,809
kWh
$1,145
-
kW-mo/yr
$787 -
02 2.2437: Recover waste heat from equipment $17,514 $8,397 - - - $17,514
-
MMBtu
03 2.7261: Install timers and/or thermostats $1,950 $865 $1,870
20,992
kWh
- $80 -
04 2.7111: Reduce illumination to minimum necessary levels $6,089 $188 $5,501
61,326
kWh
$339
-
kW-mo/yr
$249 -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $16,871 $22,132 $15,237
171,208
kWh
$943
-
kW-mo/yr
$691 -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $894 $558 $806
9,051
kWh
$54
-
kW-mo/yr
$34 -
TOTAL RECOMMENDED $62,537 $33,140 $40,701
455,386
kWh
$2,481
-
kW-mo/yr
$1,841 $17,514
-
MMBtu
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs