| Assessment Year | 2019 |
|---|---|
| Principal Product | Turbine Blade Coatings |
| NAICS | 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
| SIC | 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
60,000
ft2
|
| Annual Production | 6,500
units
|
| Production Hrs. Annual | 7,500
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $226,269 | 3,661,200 |
kWh
|
$0.062 |
| Electricity Demand | $114,841 | 8,907 |
kW-mo/yr
|
$12.89 |
| Electricity Fees | $18,100 | - |
|
- |
| Natural Gas | $303,385 | 35,616 |
MMBtu
|
$8.52 |
| TOTAL YEARLY COSTS | $662,595 | |||
| RECOMMENDED SAVINGS* | $56,176 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,851 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,041 | $3,585 |
$4,172
67,500
kWh
|
$1,857
-
kW-mo/yr
|
$320 |
$(-2,308.0)
-
MMBtu
|
- | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,933 | $50 |
$1,230
19,896
kWh
|
$606
-
kW-mo/yr
|
$97 | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,910 | $1,395 |
$1,989
32,192
kWh
|
$774
-
kW-mo/yr
|
$147 | - | - | |
| 04 | 2.4226: Use / purchase optimum sized compressor | $36,500 | $104,362 | - | - | - | - |
$36,500
-
gal
|
|
| 05 | 2.7135: Install occupancy sensors | $856 | $922 |
$813
13,162
kWh
|
- | $43 | - | - | |
| 06 | 2.7221: Lower temperature during the winter season and vice-versa | $5,941 | $50 |
$5,641
91,277
kWh
|
- | $300 | - | - | |
| 07 | 2.2437: Recover waste heat from equipment | $3,995 | $3,320 | - | - | - |
$3,995
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $56,176 | $113,684 |
$13,845
224,027
kWh
|
$3,237
-
kW-mo/yr
|
$907 |
$1,687
-
MMBtu
|
$36,500
-
gal
|
||
| TOTAL IMPLEMENTED | $8,851 | $1,445 |
$7,630
123,469
kWh
|
$774
-
kW-mo/yr
|
$447 | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs