Assessment Year | 2018 |
---|---|
Principal Product | processed chicken |
NAICS | 311615: Poultry Processing |
SIC | 2015: Poultry Slaughtering and Processing |
Sales Range | greater than $500 M |
# of Employees | 370 |
Plant Area |
181,000
ft2
|
Annual Production | 104,000,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $1,330,579 | 23,717,882 |
kWh
|
$0.056 | |
Electricity Demand | $284,243 | 49,011 |
kW-mo/yr
|
$5.80 | |
Electricity Fees | $51,327 | - |
|
- | |
Natural Gas | $594,443 | 71,926 |
MMBtu
|
$8.26 | |
Waste Disposal Costs | |||||
Water Disposal | $1,364,385 | 418,318 |
Tgal
|
$3.26 | |
TOTAL YEARLY COSTS | $3,624,977 | ||||
RECOMMENDED SAVINGS* | $255,493 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $34,494 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $186,843 | $100,000 | - | - | - |
$186,843
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $25,429 | $11,536 |
$21,948
391,235
kWh
|
$2,697
-
kW-mo/yr
|
$784 | - | |
03 | 2.4226: Use / purchase optimum sized compressor | $18,189 | $19,100 |
$17,412
310,380
kWh
|
$216
-
kW-mo/yr
|
$561 | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $6,476 | $500 |
$4,995
89,029
kWh
|
$1,281
-
kW-mo/yr
|
$200 | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,589 | $2,465 |
$2,182
38,903
kWh
|
$327
-
kW-mo/yr
|
$80 | - | |
06 | 2.2414: Use waste heat from hot flue gases to preheat | $15,967 | $70,000 | - | - | - |
$15,967
-
MMBtu
|
|
TOTAL RECOMMENDED | $255,493 | $203,601 |
$46,537
829,547
kWh
|
$4,521
-
kW-mo/yr
|
$1,625 |
$202,810
-
MMBtu
|
||
TOTAL IMPLEMENTED | $34,494 | $14,501 |
$29,125
519,167
kWh
|
$4,305
-
kW-mo/yr
|
$1,064 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs