Assessment Year | 2017 |
---|---|
Principal Product | Precision machined artillery |
NAICS | 332993: Ammunition (except Small Arms) Manufacturing |
SIC | 3489: Ordnance and Accessories, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 230 |
Plant Area |
120,000
ft2
|
Annual Production | 625,000
units
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $331,173 | 5,825,250 |
kWh
|
$0.057 |
Electricity Demand | $78,451 | 16,393 |
kW-mo/yr
|
$4.79 |
Electricity Fees | $43,985 | - |
|
- |
TOTAL YEARLY COSTS | $453,609 | |||
RECOMMENDED SAVINGS* | $45,704 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,784 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $28,247 | $52,665 |
$23,185
407,818
kWh
|
$3,415
-
kW-mo/yr
|
$1,647 | |
02 | 2.7135: Install occupancy sensors | $1,872 | $740 |
$1,763
31,011
kWh
|
- | $109 | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,673 | $500 |
$6,259
110,104
kWh
|
$967
-
kW-mo/yr
|
$447 | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,615 | $4,645 |
$5,344
94,006
kWh
|
$885
-
kW-mo/yr
|
$386 | |
05 | 2.7261: Install timers and/or thermostats | $1,297 | $60 |
$1,221
21,476
kWh
|
- | $76 | |
TOTAL RECOMMENDED | $45,704 | $58,610 |
$37,772
664,415
kWh
|
$5,267
-
kW-mo/yr
|
$2,665 | ||
TOTAL IMPLEMENTED | $9,784 | $5,445 |
$8,328
146,493
kWh
|
$885
-
kW-mo/yr
|
$571 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs