ITAC Assessment: UA0185
ITAC logo
ITAC Assessment: UA0185
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Refurbished military Vehicles
NAICS 336120: Heavy Duty Truck Manufacturing
SIC 3711: Motor Vehicles and Passenger Car Bodies
Sales Range $10
M
to 50
M
# of Employees 150
Plant Area 215,000
ft2
Annual Production 106
units
Production Hrs. Annual 2,000
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $163,776 1,267,575
kWh
Electricity Demand $36,076 7,690
kW-mo/yr
Electricity Fees $9,572 -
Natural Gas $23,214 2,487
MMBtu
TOTAL YEARLY COSTS $232,638
RECOMMENDED SAVINGS* $36,157 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,790

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $12,372 $25,579 $9,878
77,378
kWh
$2,158
-
kW-mo/yr
$336
02 2.7134: Use photocell controls $1,034 $830 $1,006
7,787
kWh
- $28
03 2.7261: Install timers and/or thermostats $9,904 $900 $9,635
74,571
kWh
- $269
04 2.4231: Reduce the pressure of compressed air to the minimum required $3,091 $500 $2,519
19,496
kWh
$488
-
kW-mo/yr
$84
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,414 $4,645 $7,929
61,370
kWh
$1,229
-
kW-mo/yr
$256
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $342 $85 $262
1,998
kWh
$71
-
kW-mo/yr
$9
TOTAL RECOMMENDED $36,157 $32,539 $31,229
242,600
kWh
$3,946
-
kW-mo/yr
$982
TOTAL IMPLEMENTED $10,790 $5,560 $9,197
71,155
kWh
$1,300
-
kW-mo/yr
$293
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs