Assessment Year | 2017 |
---|---|
Principal Product | Furniture |
NAICS | 337121: Upholstered Household Furniture Manufacturing |
SIC | 2512: Wood Household Furniture, Upholstered |
Sales Range | $50 M to 100M |
# of Employees | 407 |
Plant Area |
650,000
ft2
|
Annual Production | 440,000
units
|
Production Hrs. Annual | 2,500
hrs
|
Location (State) | Mississippi |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $224,063 | 2,362,436 |
kWh
|
$0.095 |
Electricity Demand | $63,967 | 8,306 |
kW-mo/yr
|
$7.70 |
Electricity Fees | $7,384 | - |
|
- |
TOTAL YEARLY COSTS | $295,414 | |||
RECOMMENDED SAVINGS* | $74,092 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,357 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $54,103 | $88,547 |
$37,959
400,240
kWh
|
$14,794
-
kW-mo/yr
|
$1,350 | |
02 | 2.7135: Install occupancy sensors | $5,103 | $11,746 |
$4,976
52,469
kWh
|
- | $127 | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,742 | $500 |
$4,213
44,418
kWh
|
$1,386
-
kW-mo/yr
|
$143 | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,999 | $2,465 |
$3,121
32,906
kWh
|
$778
-
kW-mo/yr
|
$100 | |
05 | 2.7261: Install timers and/or thermostats | $3,255 | $1,850 |
$3,174
33,463
kWh
|
- | $81 | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,890 | $987 |
$1,208
12,740
kWh
|
$651
-
kW-mo/yr
|
$31 | |
TOTAL RECOMMENDED | $74,092 | $106,095 |
$54,651
576,236
kWh
|
$17,609
-
kW-mo/yr
|
$1,832 | ||
TOTAL IMPLEMENTED | $12,357 | $16,061 |
$11,271
118,838
kWh
|
$778
-
kW-mo/yr
|
$308 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs