| Assessment Year | 2017 |
|---|---|
| Principal Product | Residential door assemblies |
| NAICS | 321911: Wood Window and Door Manufacturing |
| SIC | 2431: Millwork |
| Sales Range | $10 M to 50M |
| # of Employees | 230 |
| Plant Area |
360,000
ft2
|
| Annual Production | 875,000
units
|
| Production Hrs. Annual | 2,475
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $167,073 | 2,631,550 |
kWh
|
$0.063 |
| Electricity Demand | $11,964 | 2,524 |
kW-mo/yr
|
$4.74 |
| Electricity Fees | $70,500 | - |
|
- |
| Natural Gas | $3,786 | 254 |
MMBtu
|
$14.91 |
| TOTAL YEARLY COSTS | $253,323 | |||
| RECOMMENDED SAVINGS* | $86,638 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $47,414 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $29,064 | $1,800 |
$28,182
443,888
kWh
|
- | $882 | - | |
| 02 | 2.7135: Install occupancy sensors | $9,077 | $16,027 |
$8,802
138,647
kWh
|
- | $275 | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,883 | $34,772 |
$7,036
110,816
kWh
|
$2,547
-
kW-mo/yr
|
$300 | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $21,678 | $38,382 |
$21,020
331,082
kWh
|
- | $658 | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,273 | $2,645 |
$6,570
103,487
kWh
|
$2,422
-
kW-mo/yr
|
$281 | - | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $5,859 | $400 |
$3,562
56,096
kWh
|
$2,119
-
kW-mo/yr
|
$178 | - | |
| 07 | 4.454: Modify startup/shutdown times | $1,804 | - | - | - | $55 | $1,749 | |
| TOTAL RECOMMENDED | $86,638 | $94,026 |
$75,172
1,184,016
kWh
|
$7,088
-
kW-mo/yr
|
$2,629 | $1,749 | ||
| TOTAL IMPLEMENTED | $47,414 | $20,472 |
$43,554
686,022
kWh
|
$2,422
-
kW-mo/yr
|
$1,438 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs