| Assessment Year | 2016 |
|---|---|
| Principal Product | Medical Care |
| NAICS | 622110: General Medical and Surgical Hospitals |
| SIC | 8062: General Medical and Surgical Hospitals |
| Sales Range | $10 M to 50M |
| # of Employees | 160 |
| Plant Area |
100,000
ft2
|
| Annual Production | 5,450
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $426,150 | 4,394,759 |
kWh
|
$0.097 |
| Electricity Demand | $12,552 | 11,381 |
kW-mo/yr
|
$1.10 |
| Electricity Fees | $21,225 | - |
|
- |
| Natural Gas | $130,213 | 23,534 |
MMBtu
|
$5.53 |
| TOTAL YEARLY COSTS | $590,140 | |||
| RECOMMENDED SAVINGS* | $191,882 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $83,482 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7252: Utilize an evaporative air pre-cooler or other heat exchanger in ac system | $93,758 | $199,325 |
$49,417
509,611
kWh
|
- | $870 |
$43,471
-
MMBtu
|
|
| 02 | 2.7233: Use properly designed and sized hvac equipment | $25,491 | $80 |
$25,050
258,332
kWh
|
- | $441 | - | |
| 03 | 2.2625: Chill water to the highest temperature possible | $26,248 | $80 |
$25,794
266,002
kWh
|
- | $454 | - | |
| 04 | 2.7241: Install outside air damper / economizer on hvac unit | $14,642 | $59,120 |
$14,389
148,388
kWh
|
- | $253 | - | |
| 05 | 2.2625: Chill water to the highest temperature possible | $1,707 | $120 |
$1,677
17,291
kWh
|
- | $30 | - | |
| 06 | 2.7224: Reduce space conditioning during non-working hours | $617 | $200 |
$280
2,890
kWh
|
- | $5 |
$332
-
MMBtu
|
|
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $25,666 | $38,071 |
$24,768
255,424
kWh
|
$454
-
kW-mo/yr
|
$444 | - | |
| 08 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,753 | $1,050 |
$3,639
37,525
kWh
|
$49
-
kW-mo/yr
|
$65 | - | |
| TOTAL RECOMMENDED | $191,882 | $298,046 |
$145,014
1,495,463
kWh
|
$503
-
kW-mo/yr
|
$2,562 |
$43,803
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $83,482 | $39,601 |
$81,208
837,464
kWh
|
$503
-
kW-mo/yr
|
$1,439 |
$332
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs