Assessment Year | 2016 |
---|---|
Principal Product | Dump Truck Bodies |
NAICS | 336211: Motor Vehicle Body Manufacturing |
SIC | 3713: Truck and Bus Bodies |
Sales Range | $50 M to 100M |
# of Employees | 215 |
Plant Area |
165,000
ft2
|
Annual Production | 2,680
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $198,436 | 2,186,996 |
kWh
|
$0.091 |
Electricity Demand | $13,964 | 7,403 |
kW-mo/yr
|
$1.89 |
Electricity Fees | $18,471 | - |
|
- |
Natural Gas | $68,548 | 6,522 |
MMBtu
|
$10.51 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $77,787 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,682 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7231: Use radiant heater for spot heating | $18,939 | $26,379 | - | - | - |
$18,939
-
MMBtu
|
|
02 | 2.2437: Recover waste heat from equipment | $4,919 | $6,004 | - | - | - |
$4,919
-
MMBtu
|
|
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $19,851 | $52,188 |
$18,624
205,265
kWh
|
$775
-
kW-mo/yr
|
$452 | - | |
04 | 2.7134: Use photocell controls | $1,195 | $498 |
$1,168
12,877
kWh
|
- | $27 | - | |
05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $689 | $720 |
$643
7,090
kWh
|
$30
-
kW-mo/yr
|
$16 | - | |
06 | 2.4224: Upgrade controls on compressors | $13,905 | $14,748 |
$13,094
144,321
kWh
|
$494
-
kW-mo/yr
|
$317 | - | |
07 | 2.4226: Use / purchase optimum sized compressor | $8,491 | $3,500 |
$7,992
88,091
kWh
|
$306
-
kW-mo/yr
|
$193 | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,421 | $2,995 |
$6,075
66,959
kWh
|
$200
-
kW-mo/yr
|
$146 | - | |
09 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,377 | $300 |
$3,153
34,746
kWh
|
$147
-
kW-mo/yr
|
$77 | - | |
TOTAL RECOMMENDED | $77,787 | $107,332 |
$50,749
559,349
kWh
|
$1,952
-
kW-mo/yr
|
$1,228 |
$23,858
-
MMBtu
|
||
TOTAL IMPLEMENTED | $11,682 | $4,513 |
$11,039
121,672
kWh
|
$377
-
kW-mo/yr
|
$266 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs