Assessment Year | 1999 |
---|---|
Principal Product | Aggregate Stone |
NAICS |
n/a
|
SIC | 3281: Cut Stone and Stone Products |
Sales Range | $10 M to 50M |
# of Employees | 21 |
Plant Area |
27,000,000
ft2
|
Annual Production | 1,200,000
ton
|
Production Hrs. Annual | 3,600
hrs
|
Location (State) | Georgia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $102,273 | 2,208,382 |
kWh
|
$0.046 |
Electricity Demand | $73,496 | 9,187 |
kW-mo/yr
|
$8.00 |
Electricity Fees | $10,546 | - |
|
- |
Fuel Oil #2 | $245,000 | 49,000 |
MMBtu
|
$5.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $58,028 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $46,181 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.5123: Reduce fluid flow rates | $4,090 | $600 |
$4,090
127,784
kWh
|
- | - | - | - | |
02 | 2.4131: Size electric motors for peak operating efficiency | $9,897 | $5,660 |
$3,809
118,992
kWh
|
$6,088
-
kW-mo/yr
|
- | - | - | |
03 | 3.7311: Maintain machines to reduce leaks | $6,500 | $5,000 | - | - | - |
$6,500
-
gal
|
- | |
04 | 3.5111: Filter and reuse hydraulic oil | $1,950 | $3,500 | - | - |
$1,950
-
MMBtu
|
- | - | |
05 | 2.4133: Use most efficient type of electric motors | $3,071 | $51,281 |
$1,230
36,928
kWh
|
$1,841
-
kW-mo/yr
|
- | - | - | |
06 | 2.3137: Use power during off-peak periods | $32,520 | - | - | - | - | - | $32,520 | |
TOTAL RECOMMENDED | $58,028 | $66,041 |
$9,129
283,704
kWh
|
$7,929
-
kW-mo/yr
|
$1,950
-
MMBtu
|
$6,500
-
gal
|
$32,520 | ||
TOTAL IMPLEMENTED | $46,181 | $56,881 |
$5,320
164,712
kWh
|
$1,841
-
kW-mo/yr
|
- |
$6,500
-
gal
|
$32,520 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs