ITAC Assessment: UA0153
ITAC logo
ITAC Assessment: UA0153
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Couplings
NAICS 333613: Mechanical Power Transmission Equipment Manufacturing
SIC 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 200
Plant Area 130,000
ft2
Annual Production 1,578,118
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $494,829 6,606,543
kWh
Electricity Fees $60,868 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $157,180 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $26,459

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings
01 2.7241: Install outside air damper / economizer on hvac unit $73,794 $99,000 $70,630
942,996
kWh
$3,164
02 2.7261: Install timers and/or thermostats $25,593 $4,000 $24,496
327,047
kWh
$1,097
03 2.7142: Utilize higher efficiency lamps and/or ballasts $40,306 $65,413 $38,578
515,058
kWh
$1,728
04 2.7134: Use photocell controls $329 $118 $315
4,199
kWh
$14
05 2.4231: Reduce the pressure of compressed air to the minimum required $5,753 $100 $5,506
73,510
kWh
$247
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,300 $2,995 $5,073
67,734
kWh
$227
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $5,568 $5,780 $5,329
71,144
kWh
$239
08 2.3132: Recharge batteries on during off-peak demand periods $537 - $514
-
kWh
$23
TOTAL RECOMMENDED $157,180 $177,406 $150,441
2,001,688
kWh
$6,739
TOTAL IMPLEMENTED $26,459 $4,118 $25,325
331,246
kWh
$1,134
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs