| Assessment Year | 1987 |
|---|---|
| Principal Product | ASSEMBLY VINYL BINDERS |
| NAICS |
n/a
|
| SIC | 2782: Blankbooks, Looseleaf Binders and Devices |
| Sales Range | $5 M to 10M |
| # of Employees | 93 |
| Plant Area |
n/a
|
| Annual Production | 4,000,000
pieces
|
| Production Hrs. Annual | 4,300
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $46,586 | 603,165 |
kWh
|
$0.077 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $6,428 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,428 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $2,942 | $3,000 |
$2,942
-
kWh
|
- | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $3,036 | - |
$3,266
-
kWh
|
$(-230.0) | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $450 | - |
$450
-
kWh
|
- | |
| TOTAL RECOMMENDED | $6,428 | $3,000 |
$6,658
-
kWh
|
$(-230.0) | ||
| TOTAL IMPLEMENTED | $6,428 | $3,000 |
$6,658
-
kWh
|
$(-230.0) | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs