| Assessment Year | 2015 |
|---|---|
| Principal Product | Pressure Treated Woods |
| NAICS | 321113: Sawmills |
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $100 M to 500M |
| # of Employees | 99 |
| Plant Area |
87,019
ft2
|
| Annual Production | 56,251
thousand feet
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $545,415 | 8,742,581 |
kWh
|
$0.062 |
| Electricity Demand | $167,186 | 32,663 |
kW-mo/yr
|
$5.12 |
| Electricity Fees | $39,441 | - |
|
- |
| Wood | $374,000 | 262,992 |
MMBtu
|
$1.42 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $203,845 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,821 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Wood Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2414: Use waste heat from hot flue gases to preheat | $85,589 | $80,000 | - | - | - |
$85,589
-
MMBtu
|
|
| 02 | 2.1113: Reduce combustion air flow to optimum | $59,866 | $15,000 | - | - | - |
$59,866
-
MMBtu
|
|
| 03 | 2.2121: Increase amount of condensate returned | $36,194 | $110,000 | - | - | - |
$36,194
-
MMBtu
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,091 | $2,522 |
$6,624
106,176
kWh
|
$1,070
-
kW-mo/yr
|
$397 | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,110 | $800 |
$2,502
40,103
kWh
|
$455
-
kW-mo/yr
|
$153 | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,816 | $7,363 |
$5,827
93,399
kWh
|
$655
-
kW-mo/yr
|
$334 | - | |
| 07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $3,559 | $421 |
$2,950
47,276
kWh
|
$435
-
kW-mo/yr
|
$174 | - | |
| 08 | 2.7261: Install timers and/or thermostats | $620 | $250 |
$590
9,455
kWh
|
- | $30 | - | |
| TOTAL RECOMMENDED | $203,845 | $216,356 |
$18,493
296,409
kWh
|
$2,615
-
kW-mo/yr
|
$1,088 |
$181,649
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $11,821 | $3,572 |
$9,716
155,734
kWh
|
$1,525
-
kW-mo/yr
|
$580 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Wood Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs