| Assessment Year | 2015 |
|---|---|
| Principal Product | Valves and Fittings |
| NAICS | 332919: Other Metal Valve and Pipe Fitting Manufacturing |
| SIC | 3494: Valves and Pipe Fittings, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 175 |
| Plant Area |
500,000
ft2
|
| Annual Production | 28,000
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $2,127,795 | 33,340,704 |
kWh
|
$0.064 |
| Electricity Demand | $0.0 | 16,480 |
kW-mo/yr
|
$0.000 |
| Electricity Fees | $(-211,194.0) | - |
|
- |
| Natural Gas | $267,629 | 46,524 |
MMBtu
|
$5.75 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $286,813 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $31,351 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $88,066 | $277,510 |
$98,321
1,540,597
kWh
|
$(-10,255.0) | - | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $105,613 | $6,000 |
$155,312
2,433,600
kWh
|
$(-16,199.0) |
$(-33,500.0)
-
MMBtu
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $20,787 | $1,522 |
$23,207
363,638
kWh
|
$(-2,420.0) | - | |
| 04 | 2.4224: Upgrade controls on compressors | $54,259 | $61,169 |
$60,577
949,191
kWh
|
$(-6,318.0) | - | |
| 05 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $10,564 | $1,260 |
$11,794
184,802
kWh
|
$(-1,230.0) | - | |
| 06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,524 | $10,992 |
$8,400
131,615
kWh
|
$(-876.0) | - | |
| TOTAL RECOMMENDED | $286,813 | $358,453 |
$357,611
5,603,443
kWh
|
$(-37,298.0) |
$(-33,500.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $31,351 | $2,782 |
$35,001
548,440
kWh
|
$(-3,650.0) | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Fees Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs