ITAC Assessment: UA0136
ITAC logo
ITAC Assessment: UA0136
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product organic chemicals
NAICS 325199: All Other Basic Organic Chemical Manufacturing
SIC 2869: Industrial Organic Chemicals, Not Elsewhere Classified
Sales Range $50
M
to 100
M
# of Employees 104
Plant Area 3,789,720
ft2
Annual Production 65,500,000
lb
Production Hrs. Annual 8,064
hrs
Location (State) Alabama

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $919,449 17,695,747
kWh
Electricity Demand $180,835 44,694
kW-mo/yr
Electricity Fees $6,072 -
Natural Gas $1,358,471 366,189
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $152,370 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $15,776

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.2121: Increase amount of condensate returned $62,198 $11,224 - - - $62,198
-
MMBtu
02 2.1113: Reduce combustion air flow to optimum $15,296 $22,500 - - - $15,296
-
MMBtu
03 2.4231: Reduce the pressure of compressed air to the minimum required $35,414 $50 $30,464
586,297
kWh
$3,370
-
kW-mo/yr
$1,580 -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $15,776 $2,922 $13,826
266,081
kWh
$1,246
-
kW-mo/yr
$704 -
05 2.4224: Upgrade controls on compressors $2,916 $5,250 $2,786
53,611
kWh
- $130 -
06 2.4322: Use or replace with energy efficient substitutes $17,386 - $16,610
319,677
kWh
- $776 -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,384 $14,682 $3,233
62,215
kWh
- $151 -
TOTAL RECOMMENDED $152,370 $56,628 $66,919
1,287,881
kWh
$4,616
-
kW-mo/yr
$3,341 $77,494
-
MMBtu
TOTAL IMPLEMENTED $15,776 $2,922 $13,826
266,081
kWh
$1,246
-
kW-mo/yr
$704 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs