Assessment Year | 2014 |
---|---|
Principal Product | Lumber |
NAICS | 321113: Sawmills |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | greater than $500 M |
# of Employees | 291 |
Plant Area |
441,000
ft2
|
Annual Production | 220,000
thousand feet
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,134,903 | 39,618,738 |
kWh
|
$0.054 |
Electricity Demand | $392,026 | 94,407 |
kW-mo/yr
|
$4.15 |
Electricity Fees | $69,922 | - |
|
- |
Natural Gas | $2,830,360 | 283,036 |
MMBtu
|
$10.00 |
Wood | $1,142,070 | 1,313,391 |
MMBtu
|
$0.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $231,173 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $50,668 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Wood Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $37,621 | $16,695 |
$32,904
610,473
kWh
|
$4,052
-
kW-mo/yr
|
$665 | - | - | |
02 | 2.4224: Upgrade controls on compressors | $32,145 | $30,000 |
$27,492
510,054
kWh
|
$4,085
-
kW-mo/yr
|
$568 | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $13,047 | $100 |
$11,049
204,983
kWh
|
$1,767
-
kW-mo/yr
|
$231 | - | - | |
04 | 2.2414: Use waste heat from hot flue gases to preheat | $18,400 | $80,000 | - | - | - | - |
$18,400
-
MMBtu
|
|
05 | 2.2414: Use waste heat from hot flue gases to preheat | $129,960 | $270,000 | - | - | - |
$129,960
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $231,173 | $396,795 |
$71,445
1,325,510
kWh
|
$9,904
-
kW-mo/yr
|
$1,464 |
$129,960
-
MMBtu
|
$18,400
-
MMBtu
|
||
TOTAL IMPLEMENTED | $50,668 | $16,795 |
$43,953
815,456
kWh
|
$5,819
-
kW-mo/yr
|
$896 | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs