| Assessment Year | 2014 |
|---|---|
| Principal Product | Lumber |
| NAICS | 321113: Sawmills |
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | greater than $500 M |
| # of Employees | 291 |
| Plant Area |
441,000
ft2
|
| Annual Production | 220,000
thousand feet
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $2,134,903 | 39,618,738 |
kWh
|
$0.054 |
| Electricity Demand | $392,026 | 94,407 |
kW-mo/yr
|
$4.15 |
| Electricity Fees | $69,922 | - |
|
- |
| Natural Gas | $2,830,360 | 283,036 |
MMBtu
|
$10.00 |
| Wood | $1,142,070 | 1,313,391 |
MMBtu
|
$0.87 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $231,173 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $50,668 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Wood Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $37,621 | $16,695 |
$32,904
610,473
kWh
|
$4,052
-
kW-mo/yr
|
$665 | - | - | |
| 02 | 2.4224: Upgrade controls on compressors | $32,145 | $30,000 |
$27,492
510,054
kWh
|
$4,085
-
kW-mo/yr
|
$568 | - | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $13,047 | $100 |
$11,049
204,983
kWh
|
$1,767
-
kW-mo/yr
|
$231 | - | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $18,400 | $80,000 | - | - | - | - |
$18,400
-
MMBtu
|
|
| 05 | 2.2414: Use waste heat from hot flue gases to preheat | $129,960 | $270,000 | - | - | - |
$129,960
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $231,173 | $396,795 |
$71,445
1,325,510
kWh
|
$9,904
-
kW-mo/yr
|
$1,464 |
$129,960
-
MMBtu
|
$18,400
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $50,668 | $16,795 |
$43,953
815,456
kWh
|
$5,819
-
kW-mo/yr
|
$896 | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs